Technical Information for Mineral Plaster:
Preparation and
Application:
All
surface must be clean and free from loose or
peeling paint, grease, dirt, dust, oil and any
strange matter. Scrape or brush all loose paint,
fill open joints.
And must be scratched with a spatula after 10-15
minutes.
Mineral plaster is spilled into a large bowl
after the tin package opened. Material is mixed
after some water added according to conditions
of surface and weather. Appliance is performed
with steel trowel and a shovel within,
approximately 15 minutes, polishing and teasing
are performed and it is left to dry. Drying time
is 24 – 48 hours (in 20°C).
In rainy weathers and under a lower temperature
of 5°C practising can not be done. The surface,
on which the applying was started, should be
finished. Always use the materials that the same
production codes. If you must or if you would
like to use different colors on one surface it
is suggested that you use paper tape. Before
applying the material on the floor, apply
Acrylic Primer in the color of the material.
Plaster acquires its permanent appearance within
2 to 3 hours.
It is not health hazardous, no radioactive
elements in it.
Keep under close and dry area at 20C for 12
month. Protect from frost.
Mineral Stone usage for each Sq Meter Mineral
Plaster;
|
Size Name |
Mesh |
Microns |
For 1 Sq Meter
Mineral Plaster |
|
Thick |
13 – 32 mesh |
1300 – 500
microns |
4 - 5 kg |
|
Medium |
9 – 13 mesh |
2000 – 1300
microns |
2.7 – 3.5 kg |
|
Saten |
24 – 32 mesh |
700 – 500 microns |
1.5 – 1.8 kg |
|
Micro |
32 – 48 mesh |
500 – 300 microns |
0.8 – 1.2 kg |
|
CONDITIONS OF SALE:
1-Micro
Aggregates Package: 50lb, 25 kg polypropylene bags.
Non-returnable pallets and shrink wrap.
Mineral Plaster Package:
25 kg P.E. Bucket or 50 lb P.E. Bucket.
Non-returnable pallets and shrink wrap.
2- FOB
and CIF prices (DDP price for USA) can be
given upon request
|